ASG Plastic Factory Sets March 2027 Completion for Fourth Factory, Adding 25-30% Capacity
By News Desk ·
Key takeaways
- ASG Plastic Factory's fourth factory is 55% complete and due in March 2027, adding capacity equal to 25-30% of group output.
- The fifth factory's construction is expected to begin in Q1 2027 and finish in Q1 2028, with operations starting in Q2 2028.
- Packaging revenue rose 51% year on year in the first nine months of 2026 and contributed about 75% of group revenue.
ASG Plastic Factory Co. Expects its fourth factory to be completed in March 2027, adding production capacity equal to around 25% to 30% of the group's total output once fully operational, CEO Alanoud Al-Nasr Allah told Argaam. The company is a Saudi manufacturer of flexible plastic packaging and pipes and fittings. The project is the group's third expansion.
ASG's Fourth Factory Reaches 55% Completion
Completion of the fourth factory stood at 55% at the end of September, up from 42% at the end of June 2026, Al-Nasr Allah said in an interview with Argaam. She said the project is progressing according to the approved plan.
ASG has begun preparatory work on its fourth expansion project, the fifth factory, after leasing land from the Saudi Authority for Industrial Cities and Technology Zones (MODON) in June 2026. The company has started preparing plans and obtaining the necessary licenses. Construction of the fifth factory is expected to begin in Q1 2027 and be completed in Q1 2028, with operations scheduled to start in Q2 of the same year.
The group is financing its current expansions through retained earnings and operating cash flows, while continuing to invest in automation, product development and production process efficiency, the CEO said.
For the first nine months of 2026, operating profit rose 39% year on year. The packaging segment's revenue rose 51% and its net profit increased 40%, and the segment accounted for around 75% of group revenue and 82% of net profit. The pipes and fittings segment recorded 15% revenue growth but a 3% decline in net profit, which the CEO attributed to a competitive pricing policy aimed at strengthening market share.
Actual production volume reached around 10,700 tons in the first nine months of 2026, up 33% from the year-earlier period. Capacity utilization stood at around 78%, compared with 89% in 2025, after the addition of new production capacities, including the third factory, which is running at around 50% during its initial operating phase. The group added more than 1,000 new products during the year, bringing the total to 5,029.
Exports rose 158% in the first nine months of 2026 to more than SAR 3 million, about 2% of total revenue, while the domestic market accounts for around 98%. The group's existing financing includes a SAR 35 million interest-free loan from the Saudi Industrial Development Fund, to be repaid in four equal installments every four months starting in January 2027 and ending in January 2028.
ASG's Fifth Factory and TASI Transition Dates
The fifth factory's construction is scheduled to begin in Q1 2027, with completion in Q1 2028 and operations starting in Q2 2028. Repayment of the SAR 35 million SIDF loan begins in January 2027 and ends in January 2028. ASG continues to complete the requirements for moving from the Parallel Market (Nomu) to the Main Market (TASI), based on board approval issued in January 2026, and said it will announce any developments in due course.