Rajasthan Minister Heeralal Nagar Orders 6,000 MWh of Battery Storage Online by November 2027
By News Desk ·
Key takeaways
- Rajasthan Energy Minister Heeralal Nagar set a December 2026 to November 2027 window for completing 6,000 MWh of battery energy storage projects.
- JSW Energy was directed to finish its 250 MWh projects at Giral and Suratgarh by December 2026.
- The projects were awarded under the Centre's Viability Gap Funding and Power System Development Fund schemes at Rs 1.77 lakh to Rs 2.85 lakh per MW per month.
Rajasthan Energy Minister Heeralal Nagar has directed developers to complete all 6,000 MWh of battery energy storage system projects in the state between December 2026 and November 2027, warning of strict action against delays. The Times of India reported that Nagar reviewed the projects' progress at a meeting in Jaipur on November 24.
Nagar Reviews 6,000 MWh of Storage Projects
The review at Vidyut Bhawan covered project timelines, construction activity, land availability, grid connectivity and pending approvals. Officials from the Energy Department, Rajasthan Rajya Vidyut Utpadan Nigam and developers selected by NTPC Vidyut Vyapar Nigam attended. Nagar asked officials of the state power generation corporation to monitor progress.
Nagar directed JSW Energy to complete its 250 MWh projects at Giral and Suratgarh by December 2026. Completion timelines for the remaining projects run from December 29, 2026, to November 7, 2027. The minister said developers would face strict action if projects were not completed on time, and assured them the state government would provide coordination and support on implementation issues.
The projects were awarded under the Centre's Viability Gap Funding and Power System Development Fund schemes. The work orders include 1,000 MWh under the state component with a two-hour, two-cycle configuration, 1,000 MWh under the central component with the same configuration, and 2,000 MWh each under the PSDF scheme, with two-hour, two-cycle and four-hour, one-cycle configurations respectively. Awarded rates ranged from Rs 1.77 lakh to Rs 2.85 lakh per MW per month, which the state secured at the time as the lowest rates in the country. Once commissioned, the projects are expected to support renewable energy integration, grid stability and reliable power supply, and to help provide electricity at lower rates during peak demand.
Rajasthan Rajya Vidyut Utpadan Nigam's Role
Rajasthan Rajya Vidyut Utpadan Nigam, the state power generation corporation, was founded in 2000 and is headquartered in Jaipur, according to akta.pro company records. The same records list a headcount range of 251 to 500 and revenue and valuation estimates of $1 billion to $5 billion each. The corporation's officials attended the November 24 review and were asked to monitor developer progress.
Battery Storage Approvals Elsewhere
Ameren received state regulatory approval on November 12 to build three battery systems and two solar plants in Missouri, including 545 megawatts of battery capacity and 400 megawatts of solar, Yahoo reported. Energy-Storage.News reported on November 13 that Lacour Energy referred a wind-plus-storage site with a 4,000MWh battery to Australia's EPBC Act. AGL Energy received federal environmental clearance on November 18 for its 500MWh Abermain battery storage system in Queensland, Energy-Storage.News reported.
Deadlines Through November 2027
JSW Energy's 250 MWh at Giral and Suratgarh is due by December 2026. The remaining BESS projects carry completion dates from December 29, 2026, to November 7, 2027.