Key takeaways
- Google signed a power purchase agreement for 50 MW of superhot geothermal power from Quaise Energy's Project Obsidian in Central Oregon.
- Quaise will use conventional drilling in the first phase and expects millimeter wave drilling in a second phase at Project Obsidian.
- Quaise closed a $180 million Series B round in August 2026, including a $35 million investment from Nabors Industries.
Google has signed a power purchase agreement for 50 megawatts of superhot geothermal power from Quaise Energy's Project Obsidian in Central Oregon, with delivery beginning as early as 2030. Business Wire announced the agreement on November 17, 2026.
How the Project Obsidian Agreement Works
Quaise Energy said the power is slated to support Google's existing data center operations in The Dalles, Oregon, and the region's communities. The first phase of development will use conventional drilling technology to reach superhot geothermal conditions at commercial scale. The second phase is expected to be the first in the world to use millimeter wave drilling, a technology designed to access superhot conditions worldwide.
Quaise describes superhot geothermal as generating up to 10 times more clean power per well than traditional geothermal systems, which the company says are limited to regions with naturally occurring hot water reservoirs rarely exceeding 400°F. Quaise is developing Enhanced Geothermal Systems at superhot conditions and advancing millimeter wave drilling that can plug into existing drilling rigs.
"We started Quaise to make the Earth's most abundant energy source universally accessible — and this agreement marks a critical next step, not just for Quaise but for the entire clean energy sector," said Carlos Araque, CEO and President of Quaise Energy. Lucia Tian, Head of Advanced Energy Technologies at Google, said: "This collaboration with Quaise on superhot geothermal will help fuel local economic growth while helping to build a more robust and affordable energy future for Oregon."
Google has called Oregon home since 2006, when it built its first owned-and-operated data center in The Dalles. The company says its three data center campuses in Oregon have already achieved 83% carbon-free energy.
Quaise's Funding and Project Record
According to akta.pro company records, Quaise launched Project Obsidian in April 2026, targeting 50 MW of initial capacity and commercial operation by 2030 with a roadmap to more than 1 GW. The same records show a $180 million Series B round in July 2026 led by Prelude Ventures and a $25 million grant in September 2026 led by the US Department of Energy. Quaise's total funding stands at $487.3 million, and the company is pre-revenue with an estimated valuation of $250 million to $500 million.
Quaise's Run-Up to the Google Deal
In August 2026, Quaise closed a $180 million Series B equity round including a $35 million investment from Nabors Industries, raising total funding to $280 million, citybiz reported. In September 2026, Quaise was selected by the U.S. Department of Energy for up to $25 million in funding to advance Project Obsidian, according to FinancialContent Business Page. Later that month, Energyintel reported that Quaise ordered a nuclear fusion component from Japan's Kyoto Fusioneering to power its drilling method.
Project Obsidian's Construction Timeline
Quaise said Project Obsidian is expected to support 200 to 400 jobs during construction and more than 50 permanent high-skilled jobs in engineering and operations. The company's own announcement describes the project as the world's first commercial superhot geothermal power plant.