PLN Indonesia Power Breaks Ground on 4.5-MW Solar and 9 MWh Battery Plant in Nusa Penida
By News Desk ·
Key takeaways
- PLN Indonesia Power began construction of a 4.5-MW hybrid solar plant with a 9 MWh battery storage system in Nusa Penida, Bali, on November 17, 2026.
- The plant is expected to generate about 8.8 million kWh annually and construction is scheduled to take 12 months.
- Nusa Penida's peak electricity load reached 18 MW in 2026, up 12 percent from the previous year, according to President Director Bernadus Sudarmanta.
PT PLN Indonesia Power has begun construction of a 4.5-megawatt hybrid solar power plant paired with a 9-megawatt-hour battery energy storage system in Nusa Penida, Bali, the company announced at a groundbreaking ceremony on November 17, 2026. ANTARA News reported the project is expected to generate approximately 8.8 million kilowatt-hours of electricity annually. PLN Indonesia Power is a subsidiary of Indonesia's state electricity company PLN that develops and operates power generation, including renewable energy infrastructure.
Inside the Nusa Penida Solar and Battery Project
President Director Bernadus Sudarmanta said the project was a strategic step toward optimizing solar energy use while supporting a cleaner, more reliable and sustainable electricity system. The plant will occupy an 8.2-hectare site and use 8,608 bifacial monocrystalline photovoltaic modules, each with a capacity of 720 watt-peak. The battery system will use lithium iron phosphate technology.
An Energy Management System and a Supervisory Control and Data Acquisition system will coordinate generation and storage, scheduling energy use, stabilizing output and supplying power during periods of high demand. Sudarmanta said the project responds to rising local demand. "Electricity demand in Nusa Penida continues to rise. In 2026, peak load reached 18 MW, up 12 percent from the previous year," he said. "By integrating a solar power plant with a Battery Energy Storage System (BESS), we aim to provide a more efficient alternative energy supply while improving the reliability of Nusa Penida's electricity system," he added.
Larger Hybrid Projects Elsewhere
Other developers have announced larger solar-plus-storage builds in recent days. PV Tech reported on November 13, 2026, that DS1 was selected to construct the 300MW Jonova PV project in Lithuania, a hybrid development including 140MW of onshore wind and 320 MWh of storage, with full commercial operation targeted for 2027. SolarQuarter reported the same day that Masdar completed its $950 million Lockhart Solar and Storage complex in California, with 365 MW of solar and 173.7 MW of storage. PR Newswire reported on November 10, 2026, that Terra-Gen held a ribbon-cutting for the same $950 million Lockhart project in San Bernardino County. POWER Magazine reported on November 9, 2026, that Arevon's Eland Solar-plus-Storage project in Kern County, California, combines 758 MW of solar with 300 MW/1,200 MWh of battery storage.
Construction Timeline
Construction of the Nusa Penida plant and battery system is scheduled to take 12 months, starting on June 6, 2026, according to the company's project announcement.