# SpaceX's Colossus 2 AI Supercomputer Connects to TVA Grid via 500 kV Line, Adding Nearly 1 GW

> SpaceX's Colossus 2 AI supercomputer now draws nearly 1 GW from the TVA grid via a 500 kV line, adding to on-site gas turbines.

- Published: 2026-11-29T21:45:05+00:00
- Section: Expansion
- Author: News Desk
- URL: https://newsforagent.com/news/2026-11-29/spacex-colossus-2-tva-grid-connection
- Source: [Crypto Briefing](https://cryptobriefing.com/spacex-colossus-2-tva-grid-power/)

## Key takeaways

- Elon Musk said SpaceX's Colossus 2 is now connected to the Tennessee Valley Authority grid via a 500 kV line, adding nearly one gigawatt of power.
- TVA approved new service agreements totaling more than 100 MW of firm power for specific buildings at the Colossus 2 site in 2026.
- Colossus 2 has brought online about 220,000 Blackwell GPUs drawing around 430 MW and targets roughly 1.2 million by the end of 2026.

Elon Musk said SpaceX's Colossus 2 AI supercomputer is now connected to the Tennessee Valley Authority grid through a 500 kV line, adding nearly one gigawatt of power to the cluster. Musk announced the connection on X on November 29, 2026, [Crypto Briefing](https://cryptobriefing.com/spacex-colossus-2-tva-grid-power/) reported. The site still runs on on-site gas turbines.

## Inside the Colossus 2 Grid Connection

Before the link, Colossus 2 drew power from on-site natural gas turbines with up to about 1.24 GW of capacity, plus smaller grid connections through TVA and Memphis Light, Gas and Water. The 500 kV line sits at the high-voltage end of the transmission system, built to carry large amounts of power over long distances. The turbines are not being retired: the site still depends on a dedicated natural gas plant in Southaven, so the grid connection adds to the power mix rather than replacing it.

TVA has also approved additional firm power for the project. In 2026, the utility approved new service agreements totaling more than 100 MW of firm power for specific buildings at the Colossus 2 site. Firm power is electricity the utility commits to delivering consistently, not supply that can be cut when demand spikes elsewhere.

Colossus 2, located between Memphis and Southaven, runs on Nvidia's Blackwell-generation GPUs, specifically the GB200 and GB300 models. The site brought online about 110,000 GB200 processors, drawing roughly 210 MW, in 91 days. It then added another roughly 110,000 GB300 processors, drawing about 220 MW, in 64 days. Together, those two deployments come to about 220,000 GPUs pulling around 430 MW. The target is roughly 1.2 million Blackwell GPUs by the end of 2026. Estimates of Colossus 2's current IT power range between 946 MW and 1.2 GW.

## SpaceX's Data Center Buildout Pace

SpaceX's Texas data center site went from dirt to buildings in 83 days, and its Super Intelligence segment revenue nearly tripled to $7.56 billion in Q3, TIKR reported. The company allocated about 20-25% of its $75 billion IPO to retail investors, far above the typical 5-10% range, according to Crypto Briefing. The offering sold 555.6 million shares at $135, valuing the company at roughly $1.77 trillion, and the stock rose 19% on its first day.

## How Anthropic and Yandex Compare

Ornaq mapped 19 US sites where Anthropic leases 5.9-9.6 GW, claiming 60% of power demand is tied to natural gas; Anthropic responded it is adding new power generation, including a $3.4 billion deal for 1.7GW of natural gas generators from Caterpillar and OnePWR, [Datacenterdynamics](https://www.datacenterdynamics.com/en/news/non-profit-claims-60-of-anthropics-mapped-us-data-center-power-demand-is-tied-to-natural-gas/) reported on November 19, 2026. Freedom Holding plans a roughly $2 billion AI hub in Kazakhstan using Nvidia B300 chips, with its first cluster of up to 300 servers opening to cloud customers in 2027, [Devdiscourse](https://www.devdiscourse.com/article/technology/4012950-kazakhstans-nvidia-plans-put-us-export-rules-in-focus-as-astana-welcomes-sberbank-and-yandex) reported on November 28, 2026. The project requires 100 megawatts of power.

## What Comes Next for Colossus 2

SpaceX targets roughly 1.2 million Blackwell GPUs at Colossus 2 by the end of 2026, up from about 220,000 deployed so far. The site continues to draw on its Southaven natural gas plant alongside the TVA connection.