# Land Acquisition Starts for Chutka Nuclear Plant as Bassi Becomes First Project Under Shanti Act

> Land acquisition has begun for NPCIL's Chutka nuclear plant in Mandla and NTPC's Bassi project in Neemuch, the first taken up under the Shanti Act.

- Published: 2026-11-29T04:26:46+00:00
- Section: Expansion
- Author: News Desk
- URL: https://newsforagent.com/news/2026-11-29/npcil-chutka-bassi-nuclear-land-acquisition
- Source: [The Times of India](https://timesofindia.indiatimes.com/india/land-acquisition-begins-for-first-nuclear-project-under-shanti-act-in-mp/articleshow/136259357.cms)

## Key takeaways

- Land acquisition for the Chutka nuclear plant in Mandla district, built by NPCIL, is underway alongside NTPC's Bassi project in Neemuch.
- Power secretary Pankaj Agarwal said clear pathways for Madhya Pradesh nuclear projects will be in place by the end of this financial year.
- Power minister Manohar Lal said 25-30 locations have been identified for nuclear projects across India.
- NPCIL operates 24 commercial reactors totalling 8,780 MW and has 7 reactors totalling 6,100 MW under construction.

Land acquisition has started for a nuclear power plant in Bassi village in Madhya Pradesh's Neemuch district, the first project taken up after the Shanti Act was enacted, while acquisition for another plant in Chutka village in Mandla district is also underway, [The Times of India](https://timesofindia.indiatimes.com/india/land-acquisition-begins-for-first-nuclear-project-under-shanti-act-in-mp/articleshow/136259357.cms) reported, citing Union power secretary Pankaj Agarwal.

## Bassi and Chutka Land Acquisition Details

Agarwal said on Saturday that Madhya Pradesh has taken the lead in developing nuclear power projects and that many more sites were discussed at the minister's conference. "By the end of this financial year, we will have clear pathways," he said.

The Shanti Act was enacted in December last year, opening the highly regulated sector to private investment. [National Thermal Power Corporation](https://akta.pro/company-profiles/00026rh/national-thermal-power-corporation) is developing the Bassi plant, while [Nuclear Power Corporation of India](https://akta.pro/company-profiles/0002vkq/nuclear-power-corporation-of-india) will build the Chutka plant.

Agarwal said the government was also exploring the use of old thermal power plant sites for nuclear projects as coal-based units are phased out. He noted that settlements had come up around several old thermal plants, making such use difficult without affecting local communities, and said alternative sites had been identified. He also referred to small modular reactors, which could reduce the requirement for exclusion zones and water.

Union power minister Manohar Lal said on Friday that 25-30 locations had been identified for nuclear projects and that states had been urged to identify more sites.

## NPCIL's Operating Fleet and Construction Pipeline

NPCIL is India's state-owned nuclear utility, operating 24 commercial reactors totalling 8,780 MW and selling electricity to state electricity boards under long-term regulated power purchase agreements, according to akta.pro [company records](https://akta.pro/company-data). The same records show 7 reactors totalling 6,100 MW under construction: RAPP-8 at 700 MW, GHAVP 1 and 2 at 2x700 MW, and KKNPP 3 and 4 and KKNPP 5 and 6 at 2x1000 MW each.

## Earlier Moves on India's Nuclear Programme

In August 2026, The Times of India reported that NPCIL was proposing a consulting subsidiary to offer design, engineering, operations, management and regulatory support to private companies building pressurised heavy water reactors, following the Shanti Act 2025. The same month, The Times of India reported that Adani Group, Jindal Steel and state-run NTPC planned to deploy indigenous nuclear reactors to speed capacity expansion and reduce construction delays. In August 2026, Business Today reported that NPCIL had sought enhanced financial and administrative autonomy for its Board, similar to Maharatna status, to expedite decision-making for a target of 100GW of nuclear capacity by 2047.

## What Comes Next for Madhya Pradesh Nuclear Projects

Agarwal said clear pathways for the Madhya Pradesh projects would be in place by the end of this financial year.

## Companies in this story

- [Nuclear Power Corporation of India company profile](https://akta.pro/company-profiles/0002vkq/nuclear-power-corporation-of-india) · website: https://www.npcil.nic.in/index.aspx
- [National Thermal Power Corporation company profile](https://akta.pro/company-profiles/00026rh/national-thermal-power-corporation) · website: http://www.ntpc.co.in

---
News for Agent · https://newsforagent.com/llms.txt