Rosatom Loads Beloyarsk BN-800 With Fuel Recycled From Its Own Plutonium

By ·

Key takeaways

  • Engineers at Beloyarsk unit 4 loaded an experimental assembly of twice-recycled MOX fuel into the 880 MW BN-800 sodium-cooled fast reactor.
  • Rosatom Director General Alexei Likhachev said the company has moved from theory to practice in closing the nuclear fuel cycle at fast reactors.
  • Russia plans about 30 GW of new nuclear capacity, with BREST-OD-300 due in 2029 and the BN-1200M in 2035.

Rosatom has loaded an experimental assembly of twice-recycled mixed-oxide fuel into the 880 MW BN-800 sodium-cooled fast-neutron reactor at Beloyarsk unit 4 in the Urals, the state nuclear corporation said on November 27. The plutonium in the fuel came from a MOX assembly that had already completed a full cycle inside the same reactor, Yahoo reported.

How the Beloyarsk Fuel Test Works

Until now the BN-800 ran on MOX made with plutonium recovered from the spent fuel of conventional thermal reactors, according to Nuclear Engineering International. The new assembly is a single test unit rather than a full core, and the work is being carried out under licence from the regulator Rostechnadzor.

"Today, we have moved from theory to practice in closing the nuclear fuel cycle at fast reactors," said Rosatom Director General Alexei Likhachev. "Having overcome another technological milestone, we are proving the viability of the very model of 'renewable' nuclear energy."

Today's light-water reactors burn less than 1% of the energy in the uranium they are fed, with the rest ending up as waste. A fast reactor that breeds plutonium and gets it back as fresh fuel can keep recycling the same material. Rosatom says this is the first time the closed cycle has been shown on a large commercial reactor rather than a prototype, a claim no independent body has yet confirmed.

The assembly's real job is to feed operating data into the next generation of Russian fast reactors: the BN-1200M planned as Beloyarsk unit 5, which Likhachev says will be operating in the next decade, and the lead-cooled BREST-OD-300 being built at Seversk in Siberia's Tomsk region.

Rosatom's Reactor Pipeline

Rosatom is the Russian Federation's state nuclear energy corporation, integrating over 550 enterprises and 415,000 employees across the full nuclear value chain, according to akta.pro company records. The same records describe an order book of 41 energy blocks in 11 countries at different stages of implementation, which they call the world's largest portfolio of nuclear plant construction orders.

BREST-OD-300 is due to start in 2029. Beloyarsk received a siting licence for the BN-1200M in April 2025, with first concrete expected around 2027 and commissioning in 2035, according to the World Nuclear Association. Russia plans to commission about 30 GW of new nuclear capacity over the long term, President Vladimir Putin said in August.

Earlier Rosatom Milestones

On November 24, Rosatom said it plans to start Tianwan nuclear plant unit 8 in the first quarter of 2027, with fuel-loading preparations under way after hot testing, Interfax reported. On November 26, Likhachev said the Zaporozhye nuclear power plant is safe and stable, operating on internal power since that morning, according to TASS. On November 18, Likhachev said cargo volume on the Northern Sea Route crossed 40 million metric tons for the first time, surpassing the previous record of 37 million, TASS reported.

What Comes Next for the Closed Cycle

The BREST-OD-300 unit is scheduled to start in 2029, and the BN-1200M is targeted for commissioning in 2035. Rosatom's own announcements carry the programme details.