# NTPC Awards Pace Digitek Two of Four Khavda BESS Blocks Totaling 1,800 MWh

> Pace Digitek secured two 300 MW/900 MWh blocks in NTPC's 3,300 MWh Khavda BESS tender, with L&T and Sterling and Wilson taking the other two packages.

- Published: 2026-11-28T05:45:45+00:00
- Section: Contracts & Customers
- Author: News Desk
- URL: https://newsforagent.com/news/2026-11-28/pace-digitek-ntpc-khavda-bess-blocks
- Source: [SolarQuarter](https://solarquarter.com/2026/11/28/ntpc-awards-3300-mwh-khavda-bess-epc-contracts-to-pace-digitek-lt-and-sterling-and-wilson/)

## Key takeaways

- Pace Digitek won Block 1 and Block 2 of NTPC's Khavda BESS project, each 300 MW/900 MWh, for a combined 600 MW/1,800 MWh.
- L&T Renewables with L&T Electronic Products and Systems took Block 3 at 300 MW/900 MWh, and Sterling and Wilson Renewable Energy took Block 4 at 200 MW/600 MWh.
- NTPC issued the tender in September 2026 for four blocks at Pooling Substation-1 in Khavda, Gujarat, totaling 1,100 MW/3,300 MWh.

NTPC has awarded Pace Digitek the EPC contracts for two of four blocks in its 3,300 MWh battery energy storage project at the NTPC Renewable Energy Limited Khavda Solar Plant in Gujarat, each block sized at 300 MW/900 MWh. [SolarQuarter](https://solarquarter.com/2026/11/28/ntpc-awards-3300-mwh-khavda-bess-epc-contracts-to-pace-digitek-lt-and-sterling-and-wilson/) reported the awards on November 28, 2026.

## Pace Digitek's Two Khavda Blocks

[Pace Digitek](https://akta.pro/company-profiles/00004j5/pace-digitek) secured Block 1 and Block 2, which together represent 600 MW/1,800 MWh. [L&T](https://akta.pro/company-profiles/00hk8jn/l-t-energy) Renewables and L&T Electronic Products and Systems jointly won Block 3 at 300 MW/900 MWh, and [Sterling and Wilson Renewable Energy](https://akta.pro/company-profiles/0003g2g/sterling-and-wilson-renewable-energy) took Block 4 at 200 MW/600 MWh. The four blocks combine to 1,100 MW/3,300 MWh at Pooling Substation-1 in Khavda.

NTPC issued the tender in September 2026. Each block connects at the 33 kV level of its designated solar plant, and the EPC contractors handle turnkey execution: design, engineering, manufacturing and supply, transportation, storage, installation, testing and commissioning. The scope also covers bus extension work linking the batteries to the existing 33 kV pooling switchgear.

Pace Digitek is a Bangalore-listed infrastructure solutions company that makes utility-scale battery energy storage systems, telecom DC power products and optical fiber infrastructure for Indian government utilities including NTPC, NLC, DVC and BSNL, according to [company records](https://akta.pro/company-data). Sterling and Wilson Renewable Energy said on November 23, 2026 that it had secured three domestic renewable orders worth over Rs 2,050 crore, including a 600 MWh BESS project, Financial Express reported.

## Pace Digitek's Storage Order Book

Pace Digitek's board approved ₹200 crore of capital expenditure in June 2026 to expand BESS manufacturing capacity from 5 GWh to 10 GWh, according to akta.pro company records. The same records show FY26 full-year revenue of ₹2,641.3 crore, up 8.3% year on year, and a total executable order book of ₹11,338 crore at FY26 end across its energy and telecom segments. Management guided FY27 revenue to ₹3,200-3,400 crore.

## Earlier NTPC and BESS Wins

On November 16, 2026, CNBC TV18 reported that Pace Digitek received a ₹2,691.3 crore Letter of Award from NTPC Green Energy for a 600 MW/1,800 MWh battery storage project at the Khavda Solar Plant. In October 2026, Machine Maker reported that subsidiary Lineage Power won a ₹488.46 crore BESS order from NTPC GE Power Services for the Barh Super Thermal Power Project. TradingView reported on November 19, 2026 that Lineage Power won a INR194.06mn order from Insolare Energy for a battery energy storage system, due for completion by December 2026.

## What Comes Next at Khavda

The Khavda BESS project is expected to support renewable energy integration and power availability beyond solar generation hours, NTPC said.

## Companies in this story

- [PACE Digitek company profile](https://akta.pro/company-profiles/00004j5/pace-digitek) · website: https://www.pacedigitek.com
- [Sterling and Wilson Renewable Energy company profile](https://akta.pro/company-profiles/0003g2g/sterling-and-wilson-renewable-energy) · website: https://www.sterlingandwilsonre.com
- [L&T Energy company profile](https://akta.pro/company-profiles/00hk8jn/l-t-energy) · website: https://lntenergy.com

---
News for Agent · https://newsforagent.com/llms.txt