  • ACEN plans to add 500MW of solar capacity from the 200-MW San Marcelino and 300-MW Palauig projects in Zambales in the first half of 2027.
  • ACEN is complementing the solar parks with 800MW of battery energy storage systems across three projects in Zambales.
  • Pagasa classified the prevailing El Niño as very strong in a climate advisory issued on November 3.

ACEN Corp. plans to add 500 megawatts of solar capacity and 800 megawatts of battery energy storage to the Philippine grid in the first half of 2027, with projects in Zambales. The Inquirer reported the plan on November 28. ACEN is the listed renewable energy arm of the Ayala Group.

ACEN's Zambales Solar and Storage Projects

The solar capacity will come from two parks under construction in Zambales: the 200-MW San Marcelino project and the 300-MW Palauig project. ACEN is complementing the solar facilities with 800 MW of battery energy storage systems across three projects in Zambales. The storage systems allow producers to save excess renewable energy and inject it to the grid when demand peaks.

Eric Francia, president and CEO of ACEN, said the company is prioritizing project completion to meet local power requirements. "With the possibility of a super El Niño, our immediate priority is to accelerate the completion of projects under construction to help address the country's power requirements," Francia said in a statement. The Philippine Atmospheric, Geophysical and Astronomical Services Administration declared in its climate advisory issued on November 3 that the prevailing El Niño is "very strong."

ACEN maintains a portfolio of over 3,000 MW of operational and under-construction capacity in the Philippines, alongside a 7,000-MW development pipeline. Its retail electricity arm, ACEN RES, accounts for more than 50 percent of the government's Green Energy Option Program market, according to Energy Regulatory Commission data cited by the Inquirer. "We are focused on execution and ensuring that our investments translate into tangible benefits for consumers and the power system," Francia said.

ACEN's Battery Storage Financing and Capacity

According to akta.pro company records, ACEN secured approximately $78 million in financing in June 2026 to integrate battery energy storage systems at a Philippines solar PV project, addressing intermittency and the Department of Energy's new storage mandate. The same records put ACEN's attributable renewables capacity at 7 GW as of March 2026, including 2,519 MW of solar in the Philippines and 8 MW of battery. ACEN's stated goal is to reach 20 GW of renewable energy capacity by 2030.

ACEN's Recent Project Funding

In October 2026, ACEN committed an additional P3 billion to its subsidiary Giga Ace 8 for the Palauig Solar 2 and battery energy storage projects, the Inquirer reported. Earlier that month, ACEN secured a €50-million term loan from ING Bank to finance renewable energy projects and general corporate purposes, according to BusinessWorld Online. In November 2026, ACEN relinquished 13 service contracts covering nearly 5 GW of proposed solar and wind projects in Luzon, shifting focus to execution and capital efficiency, BusinessWorld Online reported.

ACEN's 2027 Project Timeline

ACEN expects the 500 MW of solar capacity from the San Marcelino and Palauig parks to reach the Philippine grid in the first half of 2027, with the 800 MW of battery storage across three Zambales projects complementing them.