TMK Energy Re-Completes Gurvantes XXXV Wells and Schedules LF-08 Drilling

By ·

Key takeaways

  • TMK Energy re-completed the LF-02 and LF-03 production wells at its Gurvantes XXXV pilot project with optimised well bores and smaller pumps.
  • LF-02 produced 25.2 million standard cubic feet of gas over a 14-day test with the pump off, then flowed at 14.4Mscf/d after restart.
  • Drilling of new well LF-08 is scheduled to begin this week and its results will guide TMK's 2027 appraisal program.

TMK Energy has re-completed the LF-02 and LF-03 production wells at its Gurvantes XXXV pilot well project in Mongolia's South Gobi Basin, with LF-02 flowing at 14.4Mscf per day after restart, TradingView reported. The company said the 2026 work program is progressing to plan.

Inside the LF-02 and LF-03 Re-Completions

TMK Energy installed optimised well bores and smaller fit-for-purpose pumps in both wells. The work followed a pressure build-up test at LF-02 that confirmed further reservoir pressure decline consistent with earlier reservoir modelling.

Over the 14-day testing period, LF-02 produced 25.2 million standard cubic feet of gas with the pump switched off, so no water was produced. Water levels rose by approximately 170 metres and the well needed fluid top-up before the pump could be pulled, while gas kept flowing. Bottomhole pressure reached 1,269 kilopascals at the top of the coal and held steady through the final week of the test, which the company interprets as at or very close to the desorption pressure at the LF-02 location.

On restart, gas production climbed to 14.4Mscf per day, close to three times the 5Mscf/d produced before the re-completion, before easing back to pre-workover rates the next day as the water column was drawn down. Chief executive officer Dougal Ferguson said: "Both wells have successfully been restarted, which confirms that the re-completions are mechanically operating and able to produce water and gas to surface." Whether the re-completions succeed will be settled over the coming months, after which TMK will decide on the same operations at LF-01, LF-04 and LF-07.

Drilling Set to Start at LF-08

Drilling at LF-08, the only additional pilot well in the 2026 program, is scheduled to begin this week. The rig arrived on location earlier this month and is waiting on the contractor's senior drilling crew, who have been working on another project in Mongolia. The well is due for completion within two weeks of drilling and will be brought into production soon after, with LF-02 shut in during the work to limit reservoir damage to either well. Ferguson said: "We remain fully funded for this work program and are continuing towards our target of proving commerciality in 2026 ahead of an appraisal period next year."

Mongolia Agreements Behind the Program

According to akta.pro company records, TMK signed a gas-to-power agreement with Dashvaanjil Group in May 2026 to develop Mongolia's coal seam gas resources for power generation, adding a second commercial pathway. In February 2026 the company signed a memorandum of understanding with Mongolia's Ministry of Energy to study adding coal seam gas to national energy policy, starting with peak-load power generation. The same records show a December 2024 binding memorandum with Jens Energie LLC for offtake of early-stage gas from the pilot wells, converted to electricity for local customers.

Earlier Steps at Gurvantes XXXV

In July 2026, TMK appointed US engineer Steve Skinner as chief operating officer to lead commercialisation of Gurvantes XXXV, The Sydney Morning Herald reported. The newspaper reported in June 2026 that Danny Chong joined as production manager with more than 16 years of experience, and that Elsa Gallina was elevated to joint company secretary.

What Comes After LF-08

Results from LF-08 are expected to guide TMK's 2027 appraisal program, which is in the planning phase.