Bombay High Court Stays Rs 238 Crore Award Against MMRDA in Lodha Wadala Dispute

By ·

Key takeaways

  • The Bombay High Court stayed enforcement of a Rs 238 crore arbitral award against MMRDA in favour of Lodha Developers.
  • MMRDA must deposit Rs 145 crore with the court within six weeks for the stay to hold.
  • Justice NJ Jamadar upheld the arbitrator's finding that MMRDA's tender notice was fraudulent but refused an unconditional stay.

The Bombay High Court has stayed enforcement of an arbitral award requiring MMRDA to pay Lodha Developers Rs 238 crore for losses on its Wadala project, on condition that the authority deposits Rs 145 crore with the court within six weeks. The Times of India reported the conditional order on November 25, 2026.

Inside the Wadala Award Ruling

MMRDA had sought an unconditional stay on execution of the award dated October 17, 2025, passed by a sole arbitrator. Justice NJ Jamadar found nothing inherently wrong with the award but directed MMRDA to deposit the entire principal amount and 50 percent of the compensation awarded in court within six weeks, subject to which the award remains stayed until MMRDA's petition is finally disposed of.

In March 2010, MMRDA invited bids for a 25,000 square metre plot for a commercial project with a permissible built-up area of 4,95,000 square metres, on a 65-year lease at a reserve price of Rs 50,000 per square metre, subject to a height clearance limit set by the Civil Aviation Department. MMRDA selected Lodha Developers after its winning bid of Rs 81,818 per square metre and a total premium of Rs 4,050 crore.

A proposed 101-storey tower was reduced in size and floors after the Airports Authority of India granted clearance for only 131.56 metres instead of the 530 metres the builder sought. The arbitrator considered the loss from cancellation of bookings for 287 flats above the 42nd floor and loss of profit.

The court said "character of the representation made by the MMRDA in the offer document is at the nub of the controversy." It noted the arbitrator concluded the tender notice amounted to a misrepresentation and was fraudulent under the Contract Act, and held that view "can neither be said to be perverse nor facially untenable." The court observed that Lodha Developers was induced to bid at the higher rate on the incorrect representation that 4,95,000 square metres of built-up area would be available, and said it was "not inclined to grant an unconditional stay of the execution and operation" of the award.

Lodha Developers' Scale and Recent Deals

Lodha Developers (Macrotech Developers Ltd) is India's largest listed real estate developer by sales, delivering residential projects across MMR, Pune, Bengaluru, Delhi-NCR and London, plus a 660-acre green data centre park at Palava, according to akta.pro company records. The same records show FY26 pre-sales of Rs 20,530 crore, up 16% from Rs 17,630 crore in FY25, and Q1 FY27 pre-sales of Rs 4,629 crore, with full-year guidance of Rs 24,000 crore.

Earlier Lodha Developers Disclosures

On November 2, 2026, Mumbai police registered a fresh FIR against former Lodha Developers director Rajendra Lodha over an alleged Rs 6.67 crore property fraud involving a South Mumbai flat, India Today reported. On October 31, 2026, Mint reported that Lodha Developers launched Lodha Pantheon, a ₹1,600-1,700 crore office project in Gurugram, its first NCR venture. On August 31, 2026, ScanX reported that Lodha Developers acquired the remaining 20% stake in Bellissimo Infratech Private Limited for ₹73.52 crore in a cash deal, making it a wholly owned subsidiary.

What Comes Next in the MMRDA Case

MMRDA's petition against the award remains pending before the Bombay High Court, with the award stayed until its final disposal. The Rs 145 crore deposit is due within six weeks of the November 25, 2026 order.