Gilbane Starts $74.5 Million Empire AI Data Center at University at Buffalo

By ·

Key takeaways

  • Gilbane broke ground on the $74.5 million Empire AI data center at the University at Buffalo, announced by Governor Kathy Hochul on November 19.
  • The facility is exempt from New York's statewide data center moratorium and will initially use up to five megawatts.
  • Gilbane targets substantial completion in late 2027, while the state expects construction to finish by early 2028.

Gilbane has broken ground on the $74.5 million Empire AI data center at the University at Buffalo, a project New York Governor Kathy Hochul announced on November 19. Yahoo published the Construction Dive report. The facility is exempt from New York's statewide data center moratorium.

Inside the Buffalo Data Center Build

The center will initially use up to five megawatts, Roger Treichler, a senior project executive at Gilbane, told Construction Dive. Gilbane targets substantial completion for late 2027, while the state expects construction to reach completion by early 2028, according to the news release.

The University at Buffalo plans to use heat from the new facility to warm campus buildings, according to the release. The center will use clean hydropower and connect to the university's Baker Chilled Water Plant, according to the governor's announcement. A system of pipes, geothermal wells and advanced heat pump technology will let the university recover energy from high-performance computing infrastructure and redistribute it back to the campus, reducing overall energy consumption.

In July, Hochul paused certain state environmental permits for new data centers in order to study the effects on energy demand and water use. The executive order exempts facilities primarily used for research or education and specifically names the Empire AI consortium.

The facility will house the Empire AI Gamma supercomputer and add on to two earlier systems that already serve researchers, according to the release. The second system, a $40 million supercomputer in downtown Buffalo, has 11 times the AI training capacity of the first, which was launched in 2024, according to the state.

Finishing touches will continue on the site after substantial completion in 2027, Treichler said. Remaining work includes testing building systems and commissioning the facility before operations begin in 2028, he said.

"As construction manager, Gilbane is proud to help deliver a facility that will expand access to powerful computing resources, helping researchers tackle critical challenges in healthcare, climate science and other areas that impact our communities," Treichler told Construction Dive. "The project also demonstrates how advanced technology construction and environmental stewardship can go hand in hand, with a plan that supports the University at Buffalo's plans to capture and reuse heat across its North Campus."

Gilbane's New York Project Record

According to akta.pro company records, Gilbane formed a design-build joint venture with Turner Construction and HOK in June 2026 for the $1.7 billion Wadsworth Center Public Health Laboratory for New York State. The same records show Gilbane was hired by Micron Technology in August 2025 to lead preconstruction and site-enabling works for a proposed $100 billion chipmaking complex in Clay, New York. Gilbane reported $7.7 billion in 2024 revenue and a $14 billion construction backlog as of its 2025 Annual Impact Report, according to the same records.

Earlier Gilbane Contracts in New York and Alaska

Gilbane Federal won a $114 million contract in November 2026 to modernize the water distribution system at Alaska's Coast Guard Base Kodiak, a project that includes replacing over 8 miles of main lines and four storage tanks, Yahoo reported. In October 2026, the Gilbane | Turner joint venture and HOK topped out the $1.7 billion Wadsworth Center Laboratory in Albany, completing its structural steel framework, according to EuropaWire. Gilbane's Keith Leal said in September 2026 that the company had said no more often in the last two years than in the previous 13 years, as it takes on major projects in upstate New York, American City Business Journals reported.

What Comes After Substantial Completion

Gilbane's substantial completion target of late 2027 precedes the state's expectation of construction completion by early 2028. Testing of building systems and commissioning are scheduled before operations begin in 2028, Treichler said.