# Quadrise Confirms $300,000 Valkor Payment as $650,000 Balance Awaits Fundraising

> Quadrise received confirmation that Valkor approved and submitted $300,000 of its Utah site licence fee, with the $650,000 balance due.

- Published: 2026-11-23T18:21:31+00:00
- Section: Partnerships
- Author: News Desk
- URL: https://newsforagent.com/news/2026-11-23/quadrise-valkor-site-licence-payment
- Source: [TradingView](https://www.tradingview.com/news/reuters.com,2026-11-23:newsml_RSW3327Ea:0-reg-quadrise-plc-valkor-payment-update/)

## Key takeaways

- Valkor Technologies confirmed to Quadrise that $300,000 of the site licence fee was approved and submitted for payment.
- The remaining $650,000 balance is expected once Valkor completes its ongoing fundraising.
- Shipment of the 600 barrels per day Multifuel Manufacturing Unit to Utah remains planned after the outstanding fees are received.

Quadrise Plc said Valkor Technologies LLC has confirmed that $300,000 of its site licence fee for the Utah project was approved and submitted for payment, with the funds now due by the end of the week. The [TradingView](https://www.tradingview.com/news/reuters.com,2026-11-23:newsml_RSW3327Ea:0-reg-quadrise-plc-valkor-payment-update/) report said the remaining $650,000 balance is expected on completion of Valkor's fundraising.

## How the Valkor Payment Schedule Stands

[Quadrise](https://akta.pro/company-profiles/000519j/quadrise), an AIM-listed supplier of MSAR® and bioMSAR™ emulsion fuels, said it received written confirmation from [Valkor](https://akta.pro/company-profiles/0023qrn/valkor) on 15 November 2026 that the $300,000 payment had been approved and submitted, with funds to arrive within days. The company announced that confirmation on 16 November 2026, and Valkor has since told Quadrise the payment will be made by the end of this week.

The $650,000 balance is tied to Valkor's ongoing fundraising process. Quadrise said shipment of the 600 barrels per day Multifuel Manufacturing Unit and associated equipment to Utah, followed by mobilisation on site, remains planned once the outstanding site licence fees are received. Joint marketing of MSAR® and bioMSAR™ opportunities in Utah is also underway.

## What Quadrise's Records Show on Utah

According to akta.pro [company records](https://akta.pro/company-data), Quadrise's Q2 2026 results disclosed material delays to the Valkor Utah project: the 500 barrels per day oil-sands pilot was pushed to commissioning in Q4 2026 and delivery of the 600 barrels per day Multifuel Manufacturing Unit to Q3, with $0.95m of a $1.0m licence fee still outstanding at that point. The same records list four funding rounds, the most recent a January 2025 grant of $65,201 from the European Climate, Infrastructure and Environment Executive Agency.

## Earlier Steps Toward the Utah Project

On 16 November 2026, Quadrise said Valkor had paid $300,000 of the $950,000 site licence fee, with the remaining $650,000 expected on completion of Valkor's fundraising, [Advfn](https://akta.pro/news-signals) reported. In September 2026, Quadrise reported that drilling had commenced at two new pilot wells at the Utah project with Valkor, with an eight-well programme expected to start later that year, targeting 1,000 barrels per day in 2027 and 500 barrels per day of pilot plant production in Q1 2027, Advfn reported.

## Quadrise's 27 November Meeting

Quadrise posted its annual report and financial statements for the year ended 30 June 2026, with its AGM scheduled for 27 November 2026, followed by an investor presentation, Advfn reported.

## Companies in this story

- [Quadrise company profile](https://akta.pro/company-profiles/000519j/quadrise) · website: https://www.quadrise.com
- [Valkor company profile](https://akta.pro/company-profiles/0023qrn/valkor) · website: https://www.valkorgroup.com

---
News for Agent · https://newsforagent.com/llms.txt