Boring Company's Nashville Loop Reaches 29% as $34 Million Airport Deal Is Finalized

By ·

Key takeaways

  • The Boring Company's Music City Loop tunnel system is at least 29% complete, with the longest tunnel at least 3,681 feet.
  • Crews are on pace to reach Nashville International Airport in mid-January 2028, a couple of weeks behind the promised 2027 deadline.
  • A Metro Nashville Airport Authority Board member confirmed the agreement with The Boring Company was finalized for $34 million.

The Boring Company's Music City Loop tunnel system under Nashville is at least 29% complete, with the longest tunnel at least 3,681 feet, according to Yahoo. A Metro Nashville Airport Authority Board member confirmed the company's agreement with Nashville International Airport was finalized for $34 million.

How Far The Nashville Tunnels Have Reached

The project started next to the State Capitol on Rosa L. Parks Boulevard in February. As of October 31, the tunnel system had reached the intersection of 8th Avenue South and McGavock Street, and the company is estimated to have since made it to the Music City Center.

Each tunnel must stretch more than 10,000 feet to reach the airport. One tunnel stretches about 3,700 feet and the other about 2,300 feet, putting the first phase, which connects downtown to the airport, at about 29% finished. At the speed crews have dug so far, they are on pace to reach the airport in mid-January 2028, a couple of weeks behind their promised 2027 deadline.

The Boring Company is also ramping up hiring, including tunnel laborer positions that require five 12-hour shifts each week. "This is work for people who are comfortable in an industrial environment," Middle Tennessee State University Geosciences Professor Dr. Mark Abolins said. "They have to understand the safety requirements, and can operate in a setting with constant noise and heavy equipment."

A study released in October warned tunnel construction could increase the risk of sinkholes. Documents submitted by The Boring Company indicate ground movement remains below levels considered a concern. "Based on the reports submitted to the state so far, there has not been any ground subsidence or settling outside the range that engineers would consider acceptable," Abolins said.

The Metropolitan Nashville Airport Authority and The Boring Company signed a 40-year licensing agreement on November 18 to build the tunnel system, Aviationpros reported.

Nashville Airport's Expansion And Passenger Load

Nashville International Airport is a public-use hub operated by the Metropolitan Nashville Airport Authority, handling over 24.8 million passengers annually across four runways and 3,900 acres, according to akta.pro company records. The same records describe a $3 billion New Horizon expansion program covering landside and airside projects through 2029, and a Central Core Enhancement Project that began in June 2026 to double escalators and add elevators, with the Grand Lobby reopening targeted for December 2027.

Earlier Steps Toward The Airport Station

On October 28, 2026, Yahoo reported that the Music City Loop station at Nashville International Airport would sit next to the terminal's front door, replacing the taxi and limousine pickup area, with the deal not yet final. On September 3, 2026, Stateaffairs reported that the Nashville Airport Authority spent $450,000 on preparations for a Boring Co. tunnel as part of its special projects.

What Comes Next For The Loop

The company's own project announcement and the airport's terminal updates carry further details. The Grand Lobby reopening is targeted for December 2027, and crews are pacing toward the airport in mid-January 2028.