# Honey Badger Silver Backs C$1.8 Million Crushing Circuit Restart at PC Silver Mine

> Honey Badger Silver's board approved a C$1.8 million Phase 1 restart of the PC Silver Mine crushing circuit.

- Published: 2026-11-19T14:14:54+00:00
- Section: Expansion
- Author: News Desk
- URL: https://newsforagent.com/news/2026-11-19/honey-badger-silver-pc-mill-restart
- Source: [Stock Titan](https://www.stocktitan.net/news/HBEIF/honey-badger-silver-receives-positive-mill-restart-assessment-for-pc-560nupqp79wh.html)

## Key takeaways

- Honey Badger Silver's board approved Phase 1 of Tusk Automation's restart plan for the PC Silver Mine processing plant at an estimated C$1.8 million.
- Tusk estimates Phase 2 at C$12.6 million and Phase 3 at C$21.2 million, with full concentrate production targeted for July 2028 at 1,000 tonnes per day.
- Honey Badger Silver engaged Tusk in September 2026 to evaluate reusing its $300 million mill at the Northwest Territories site.

[Honey Badger Silver](https://akta.pro/company-profiles/0000cqy/honey-badger-silver)'s board of directors approved Phase 1 of a phased restart plan for the processing plant at its 100%-owned PC Silver Mine in the Northwest Territories, refurbishing the crushing circuit at an estimated C$1.8 million. [Stock Titan](https://www.stocktitan.net/news/HBEIF/honey-badger-silver-receives-positive-mill-restart-assessment-for-pc-560nupqp79wh.html) reported the approval alongside a plant condition assessment by Tusk Automation.

## Tusk's Three-Phase Restart Plan

Tusk concluded after an on-site inspection that the existing processing infrastructure can be returned to service, and identified no conditions that would prevent its restart. The crushing circuit is substantially complete and in good mechanical condition, while the grinding and dewatering equipment is in very good condition and suitable for refurbishment and completion.

Phase 1 covers refurbishment of crushers, conveyors, electrical equipment and associated infrastructure, from ore receiving through to the fine ore storage bin. Tusk sees an opportunity to complete the work during the 2026-2027 winter season, subject to procurement, mobilization and site readiness.

Phase 2, budgeted at C$12.6 million, would complete and commission the grinding, bulk flotation and dewatering circuits and enable closed-loop proof-of-concept testing. Tusk's schedule anticipates commissioning in late 2027, followed by a 28-day pilot testing period extending into January 2028.

Phase 3, estimated at C$21.2 million, would complete the remaining flotation, dewatering, power and supporting systems needed to produce separate lead and zinc concentrates. Tusk targets July 2028 for completion and readiness for full concentrate production at 1,000 tonnes per day. The estimates include a 15% contingency, and Tusk identified approximately C$8.0 million in fuel and air transportation costs, bringing the total indicative program cost to about C$43.7 million.

Chad Williams, executive chairman of Honey Badger Silver, said: "Tusk's report is a very important milestone for Honey Badger Silver. It confirms management's thesis of using the existing process plant to a high degree, contrary to views of certain previous owners of the mine."

## Honey Badger Silver's Prairie Creek Resources

Honey Badger Silver is a Toronto-based junior miner advancing eight 100%-owned silver and critical minerals projects across Northern Canada, anchored by the permitted Prairie Creek Mine, according to akta.pro [company records](https://akta.pro/company-data). The same records list historical resource estimates at Prairie Creek of 240 million ounces of silver equivalent in the Measured and Indicated category and 167 million ounces in the Inferred category. The company closed the C$12 million acquisition of Canadian Zinc Corporation and its flagship Prairie Creek project in April 2026.

## Tusk's Earlier PC Silver Engagement

Honey Badger Silver engaged [Tusk Automation](https://akta.pro/company-profiles/000h3qs/tusk-automation) in September 2026 to evaluate reusing its $300 million mill at the PC Silver Mine, with the study to be completed by the end of that month and to inform an upcoming feasibility study, Stock Titan reported. In September 2026, the company said it would present its PC Silver Mine Preliminary Economic Assessment results at the Commodities Global Expo in Arizona and the Precious Metals Summit in Colorado, according to Yahoo.

## What Comes After Phase 1

Phase 2 and Phase 3 remain subject to further engineering, capital allocation decisions, permitting and the availability of necessary supporting infrastructure and financing. The company will continue to evaluate the phased restart alongside ongoing technical studies and project engineering.

## Companies in this story

- [Honey Badger Silver company profile](https://akta.pro/company-profiles/0000cqy/honey-badger-silver) · website: https://honeybadgersilver.com
- [Tusk Automation company profile](https://akta.pro/company-profiles/000h3qs/tusk-automation) · website: https://www.tuskautomation.com

---
News for Agent · https://newsforagent.com/llms.txt