# Protesters Urge Louisiana Regulators to Reject Entergy's Seven-Plant Plan for Meta Data Center

> Protesters in Baton Rouge urged Louisiana regulators to reject Entergy Louisiana's plan to build seven gas plants for Meta's Hyperion data center ahead of a December vote.

- Published: 2026-11-19T03:52:06+00:00
- Section: Regulation & Approvals
- Author: News Desk
- URL: https://newsforagent.com/news/2026-11-19/entergy-louisiana-meta-data-center-protest
- Source: [Yahoo](https://www.yahoo.com/news/politics/articles/protesters-urge-louisiana-regulators-reject-030335526.html)

## Key takeaways

- Protesters in Baton Rouge urged the Louisiana Public Service Commission to reject Entergy Louisiana's proposal to build seven natural gas plants for Meta's Hyperion data center in Richland Parish.
- Commissioner Davante Lewis said he has not found comfort that existing customers will be protected from stranded costs if Meta does not renew its contract after 15 and 20 years.
- Entergy said the Richland Parish data center will pay its full and fair share, and Meta's website says the partnership is expected to save customers $2.65 billion over 20 years.
- The Louisiana Public Service Commission is expected to vote on the proposal in December.

Residents, environmental advocates and students gathered in downtown Baton Rouge to urge the Louisiana Public Service Commission to reject [Entergy Louisiana](https://akta.pro/company-profiles/002wz4b/entergy-louisiana-llc)'s proposal to build seven natural gas power plants for [Meta](https://akta.pro/company-profiles/003qagv/meta)'s planned Hyperion data center in Richland Parish, [Yahoo](https://www.yahoo.com/news/politics/articles/protesters-urge-louisiana-regulators-reject-030335526.html) reported on November 19, 2026. The commission is expected to vote in December.

## Entergy's Seven-Plant Proposal for Meta's Hyperion Campus

Entergy Louisiana is a regulated electric utility subsidiary of Entergy Corporation serving more than 1.1 million customers across all 58 Louisiana parishes, according to [company records](https://akta.pro/company-data). The proposal would build seven natural gas plants to supply electricity to Meta's Hyperion data center in Richland Parish.

Protesters raised concerns about electricity costs, pollution and the potential impact on private property. Sarah Bailey, a north Louisiana landowner and representative of the Louisiana Landowners Coalition, said her family's property could be affected by a proposed transmission line connected to the project. "My great-grandmother bought this land for her family and now we're having to hire our own lawyers to protect it against corporate sellout and politician greed," Bailey said.

Public Service Commissioner Davante Lewis, who represents District 3, said he is still reviewing the proposal and wants assurances that existing customers will not be left with additional costs. "Thus far in my discovery, I have not found comfort that that has been done," Lewis said. Lewis said he is particularly concerned about what could happen if Meta does not renew its contract with Entergy or reduces its energy needs after the initial agreement. "Where is the risk of the stranded cost going? And right now, those stranded costs, if Meta decided not to renew after 15 and 20 years, go back onto the residential ratepayers," Lewis said.

Entergy said in an emailed statement that the Richland Parish data center will pay its "full and fair share" for the energy it uses, adding that other customers will not subsidize its energy needs. The company called claims that the project will raise costs for other customers false, saying the agreement includes safeguards and will bring long-term benefits to Louisiana's economy and electric system. Meta's website says the company pays the full cost of the energy its data center uses and that its partnership with Entergy is expected to save customers $2.65 billion over 20 years.

## The $22 Billion Package Behind the Hyperion Project

According to akta.pro company records, Entergy Louisiana sought LPSC approval in March 2026 for an expanded energy infrastructure package of about $22 billion covering 5.2 GW of gas generation, 2.5 GW of potential solar, three battery storage systems and 240 miles of new 500kV transmission lines to serve hyperscale data center load. The same records show Entergy Louisiana and Meta announced an expanded agreement in March 2026 to build seven natural gas power plants of more than 5,200 MW, 240 miles of 500kV transmission lines and battery storage to power the Hyperion hyperscale data center, with Meta paying the full cost of service and projected savings of $2.65 billion over 20 years. The records also show the LPSC approved the revised agreement between Entergy Louisiana and Meta, with commissioners voting to support the $22 billion energy infrastructure package.

## Earlier Steps in Entergy's Meta Power Case

In September 2026, Entergy Louisiana agreed to expand consumer advocates' access to sensitive evidence in its Meta-related power case, giving seven representatives of the Alliance for Affordable Energy and Union of Concerned Scientists limited access to Attorneys' Eyes Only materials, New Orleans City Business reported. In August 2026, Entergy Louisiana completed the sale of $1 billion in Collateral Trust Mortgage Bonds comprising two series due in 2036 and 2056, Investing.com reported, increasing the utility's total debt to $11.6 billion as it continues to fund infrastructure investments.

## December Vote Before the Louisiana Commission

The Louisiana Public Service Commission is expected to vote on Entergy's proposal in December. Lewis said he wants the commission to fully evaluate the potential costs and protections before moving forward.

## Companies in this story

- [Entergy Louisiana Llc company profile](https://akta.pro/company-profiles/002wz4b/entergy-louisiana-llc) · website: https://www.entergy-louisiana.com
- [Meta company profile](https://akta.pro/company-profiles/003qagv/meta) · website: https://www.meta.com

---