Expansion
LAX People Mover Opening Delayed to March 8, 2027 as Airport and LINXS Trade Blame
By News Desk ·
Key takeaways
- LINXS's monthly report projects the LAX People Mover could open to the public on March 8, 2027.
- LAX said the primary delay factor is LINXS' inability to complete required system demonstration testing.
- Councilmember Traci Park said she wants to know whether terminating the contract is among the city's options.
The LAX People Mover could open to the public on March 8, 2027, according to the latest monthly update from LINXS, the contractor building the automated train system. Yahoo obtained the project report, which puts the opening beyond next year's Super Bowl in Los Angeles.
LINXS Report Cites Power Deal and Site Breach
In the report, LINXS said the project is being slowed because LAX and the Los Angeles Department of Water and Power have not reached an agreement on powering the train with solar energy. The report also accuses someone suspected of being an airport employee of entering the construction site without permission and removing what LINXS described as a "key cylinder" from its Fire Command Center.
LAX dismissed those claims in a statement to 7 On Your Side. "The primary factor in the delay is LINXS' inability to complete required system demonstration testing to ensure the reliability and safety of the train," the airport said.
The dispute follows a lawsuit LINXS filed against the city this summer, in which the contractor alleged several issues, including the city's refusal to extend project deadlines. L.A. City Councilmember Traci Park, who chairs the Trade, Travel and Tourism Committee, criticized LINXS' handling of the project. "Instead of delivering a train, they have just delivered another lawsuit," Park said.
Park also said she wants more information about the city's options. "I want to know what all of our available options and remedies may include up to, and potentially including termination of the contract. I'm not saying yes or no to that, but I do want to know what our rights and remedies are," she said.
In September, a series of electrical explosions were reported while the People Mover was undergoing testing, and video obtained by 7 On Your Side showed one of the incidents. Airport officials said LINXS completed repairs related to the damage and that testing of the trains has resumed. LINXS previously told 7 On Your Side it remains committed to completing the project, but declined to comment on the latest report and the newly projected opening date.
LAX's $30 Billion Modernization
According to akta.pro company records, LAX is a City of Los Angeles-owned, LAWA-operated airport serving passengers across 9 terminals, and it is undergoing a $30 billion modernization ahead of the 2028 Olympics. The same records list the demolition and reconstruction of Terminal 5 as part of that program, and note that JetBlue relocated its LAX operations to Terminal 1 to clear Terminal 5 for demolition, coinciding with the opening of the Midfield Satellite Concourse South.
Earlier LAX Upgrades and Disputes
In September 2026, Yahoo reported that LAX was leading a nationwide overhaul of air traffic control infrastructure, introducing new technology and training; the FAA received a $12.5 billion down payment to upgrade over 4,500 sites, and LAX's simulator cut training time by 30%. In October 2026, Yahoo reported that two LAX TSA employees, Kevin Peinado and Maria Maranon, were granted a U.S. design patent for a notice holder they created from a paper towel tube and glove box.
The March 2027 Target Date
The March 8, 2027 opening date is the projection in LINXS's latest monthly update, and the report states the project could open to the general public on that date.