# BERC Clears 300 MW Solar-Plus-Storage Procurement at Rs 3.13 per kWh

> Bihar's BERC approved a 300 MW solar project with four-hour battery storage at Rs 3.13 per kWh, with SAEL required to operationalise it by June 30, 2028.

- Published: 2026-11-17T18:22:59+00:00
- Section: Regulation & Approvals
- Author: News Desk
- URL: https://newsforagent.com/news/2026-11-17/berc-approves-300-mw-solar-storage
- Source: [Construction World](https://www.constructionworld.in/energy-infrastructure/power-and-renewable-energy/bihar-approves-300-mw-solar-project-with-4-hour-battery-storage/100426)

## Key takeaways

- BERC approved procurement of 300 MW of solar power integrated with a four-hour battery energy storage system at a tariff of Rs 3.13 per kWh.
- NHPC acts as intermediary procurer and receives an additional trading margin of Rs 0.07 per kWh, while SAEL Industries India develops the project.
- The storage facility will supply 150 MW of firm electricity from 6 pm to midnight, and SAEL must operationalise the project by June 30, 2028 to qualify for transmission charge waivers.

The [Bihar](https://akta.pro/company-profiles/003z2xj/bihar-electricity-regulatory-commmission) Electricity Regulatory Commission approved Bihar State Power Holding Company's proposal to procure 300 MW of solar power integrated with a four-hour battery energy storage system at a tariff of Rs 3.13 per kWh, [Construction World](https://www.constructionworld.in/energy-infrastructure/power-and-renewable-energy/bihar-approves-300-mw-solar-project-with-4-hour-battery-storage/100426) reported on November 17, 2026. The procurement covers a 25-year power procurement agreement.

## How the BERC Procurement Will Work

The approval lets North Bihar Power Distribution Company and South Bihar Power Distribution Company obtain renewable electricity under the 25-year agreement. [NHPC](https://akta.pro/company-profiles/0000oxh/nhpc) will act as the intermediary procurer, and [SAEL](https://akta.pro/company-profiles/0000aj4/sael) Industries India has been selected as the project developer. SAEL will supply the 300 MW from a larger 1,200 MW interstate transmission system-connected renewable energy project.

The approved tariff is Rs 3.13 per kWh, with NHPC receiving an additional trading margin of Rs 0.07 per kWh. The Central Electricity Regulatory Commission adopted the competitively discovered tariff in April 2026. The storage facility will provide 150 MW of firm electricity during the evening peak period from 6 pm to midnight, shifting solar generation to periods of higher consumption.

BERC set performance requirements under which the developer must maintain at least 70 per cent of contracted peak capacity each month and 85 per cent annually. Shortfalls will attract financial penalties calculated at 1.5 times the applicable tariff for the deficient supply. The commission assessed the proposal against the national Resource Adequacy framework and Bihar's Renewable Purchase Obligation requirements through FY 2029-30.

## What the Bihar Commission Regulates

According to akta.pro [company records](https://akta.pro/company-data), the Bihar Electricity Regulatory Commission is the statutory state electricity regulator for Bihar, established under the Electricity Act, 2003, and operates from Patna under the Government of Bihar. The same records list NBPDCL and SBPDCL as regulated distribution licensees under BERC's jurisdiction, with BERC determining tariff orders and the regulatory framework for their distribution operations in North and South Bihar respectively. The records also list BSPTCL as the state transmission company regulated by BERC for transmission tariff determination and compliance monitoring.

## Earlier BERC Decisions in Bihar

In August 2026, BERC approved a joint Standard Operating Procedure submitted by South and North Bihar Power Distribution Companies for replacing service cables during smart prepaid meter installations, in Case No. 35/2025, SolarQuarter reported. That same month, BERC proposed the Bihar Electricity Grid Code, 2026, aiming to overhaul the state's power grid regulatory framework. Earlier in August 2026, BERC raised concerns over procedural delays, additional cost components and contractual issues in a petition for the procurement of 10 MW of ground-mounted solar power filed jointly by Bihar State Power Generation Company Limited and Bihar State Power (Holding) Company Limited.

## SAEL's June 2028 Deadline

SAEL Industries India is scheduled to operationalise the project by June 30, 2028. Meeting the deadline would enable a 25 per cent waiver on interstate transmission charges for the solar component and a 100 per cent waiver for electricity supplied from the co-located battery energy storage system. BERC also approved a modified Power Sale Agreement with provisions to pass on potential tariff reductions resulting from future changes in Goods and Services Tax rates.

## Companies in this story

- [Bihar Electricity Regulatory Commmission company profile](https://akta.pro/company-profiles/003z2xj/bihar-electricity-regulatory-commmission) · website: https://berc.co.in
- [NHPC company profile](https://akta.pro/company-profiles/0000oxh/nhpc) · website: http://www.nhpcindia.com/home.aspx
- [SAEL company profile](https://akta.pro/company-profiles/0000aj4/sael) · website: https://sael.co

---
News for Agent · https://newsforagent.com/llms.txt