Tata Power Unit TPREL Commissions 100.8 MW Ausa Wind Farm, Taking Operational Renewables to 7.3 GW
By News Desk ·
Key takeaways
- Tata Power Renewable Energy Limited commissioned a 100.8 MW wind project in Ausa, Latur, Maharashtra, with 28 wind turbine generators.
- The project is expected to generate about 308 million units annually and cut roughly 252,560 tonnes of CO2 each year.
- TPREL's operational renewable capacity now stands at 7.3 GW, split between 5.9 GW of solar and 1.4 GW of wind, with 4.8 GW under implementation.
Tata Power's subsidiary Tata Power Renewable Energy Limited has commissioned a 100.8 MW wind project in Ausa, Latur, Maharashtra, the company said in an announcement covered by ScanX. The plant will supply renewable power to Tata Power Mumbai Distribution and is expected to generate about 308 million units of electricity annually.
Inside the Ausa Wind Project
The Ausa facility comprises 28 Horizontal Axis Wind Turbine Generators using the SG 3.6-145 model. Tata Power said the project is expected to reduce approximately 252,560 tonnes of CO2 emissions every year.
Midway through execution, the grid connectivity plan was revised and the Extra High Voltage line configuration changed from underground cable to Monopole. The company said the revision added design, procurement and execution complexity and marked the first Monopole EHV line installation by TPREL's Wind Project Execution Division. The team incorporated the revised configuration without affecting the overall project schedule, according to the company.
With the addition, TPREL's total renewable utility capacity stands at 12.1 GW. Of that, 7.3 GW is operational, split between 5.9 GW of solar and 1.4 GW of wind, while 4.8 GW remains under various stages of implementation.
Tata Power's Renewable Capacity and Funding Record
Tata Power is a Mumbai-based power company founded in 1911, according to akta.pro company records, with installed and managed capacity of 14,101 MW across thermal, solar, wind and hydro. The same records put its clean and green energy portfolio at 7,856 MW, with 7,884 MW of operational renewable capacity.
The company profile lists total funding of $4.5 billion, including a $4.2 billion post-IPO debt round in November 2024 led by Asian Development Bank and a $223.3 million post-IPO debt round in December 2025. Praveer Sinha is CEO and Managing Director.
Earlier Steps in Tata Power's Expansion
In June 2026, Tata Power awarded Suzlon a 400 MW wind EPC order in Andhra Pradesh, taking the cumulative Suzlon-Tata Power partnership past 1 GW, according to akta.pro records. The same month, the company announced a Rs 15,000 crore investment to upgrade Mumbai's distribution network by 2029, including a 400 kV bulk power ring and 18 new substations by 2031.
On November 6, 2026, BusinessLine reported that Tata Power had installed 60 MWh battery storage projects in Mumbai's Mahalaxmi, Saki and Mankhurd areas as part of a 200 MWh BESS plan across 10 locations approved by MERC in April 2025.
What Comes Next for TPREL
Tata Power's management has retained a 2.5 GW renewable commissioning target for the year, with 4.8 GW of TPREL's renewable capacity still under implementation. The company's own announcements cover its project pipeline.