PACE Digitek Secures ₹2,691.3 Crore NTPC Green Energy Battery Storage Contract in Gujarat
By News Desk ·
Key takeaways
- PACE Digitek received a ₹2,691.3 crore Letter of Award from NTPC Green Energy for a 600 MW/1,800 MWh battery energy storage project at the Khavda Solar Plant in Gujarat.
- The contract covers supply, installation, testing, commissioning and 15 years of operations and maintenance, with completion scheduled for September 2027.
- The award follows an October Letter of Intent from BSES Rajdhani Power for a 57.5 MW/115 MWh standalone BESS project in Delhi with an estimated project cost of ₹179.4 crore.
PACE Digitek has received a ₹2,691.3 crore Letter of Award from NTPC Green Energy for a 600 MW/1,800 MWh battery energy storage project at the Khavda Solar Plant in Gujarat, CNBC TV18 reported on November 16, 2026. The contract includes supply, installation, commissioning and 15 years of operations and maintenance, with completion scheduled for September 2027.
Inside the Khavda Battery Storage Award
PACE Digitek is a Bengaluru-based infrastructure solutions company that manufactures utility-scale battery energy storage systems, telecom DC power products and optical fiber infrastructure for Indian government utilities and select private enterprises across India and Africa. The Khavda award sits within NTPC's 3,300 MWh BESS project and covers two blocks under Cluster-01, each with a capacity of 300 MW and 900 MWh.
Under the contract, PACE Digitek will handle supply and integration of the storage systems as well as their installation, testing and commissioning. The scope also includes associated civil works and operations and maintenance for 15 years. The company said the project is scheduled for completion by September 2027.
NTPC Green Energy is inviting bids for battery containers and grid-forming PCS for a 10 GW/40 GWh BESS project, with a 15-year maintenance contract under a Long Term Service Agreement, SolarQuarter reported on November 4, 2026.
PACE Digitek's Storage Order Book
According to akta.pro company records, PACE Digitek's board approved ₹200 crore of capital expenditure in June 2026 to expand BESS manufacturing capacity from 5 GWh to 10 GWh. The same records show FY26 full-year revenue of ₹2,641.3 crore, up 8.3% year on year, and a total executable order book of ₹11,338 crore as of the end of FY26, diversified across its energy and telecom segments.
Earlier NTPC and Kalpa Power Contracts
PACE Digitek's subsidiary Lineage Power won a ₹488.46 crore order from NTPC GE Power Services for 5.015 MWh BESS containers, BMS, EMS and a 12-year maintenance contract, CNBC TV18 reported in September 2026, with the contract due by December 31, 2026. In August 2026, Lineage Power received a Rs 929.3 million work order from Kalpa Power for supplying and commissioning support of a 100 MWh battery energy storage system, to be completed by 31 December 2026, Construction World reported. PACE Digitek also doubled its manufacturing capacity for battery energy storage systems to five GWh by commissioning a new production line in the Asia Pacific region, Construction World reported in August 2026.
What Comes After the Letter of Award
The Khavda project is scheduled for completion by September 2027, according to the company. The Lineage Power contract with NTPC GE Power Services is due by December 31, 2026, and the Kalpa Power work order is to be completed by 31 December 2026.