# State Grid Changzhou Crosses High-Speed Railway to Power CATL Phase VI Project

> State Grid Changzhou used drones to string a 220 kV line across the Nanjing-Hangzhou railway, supporting CATL's Phase VI project and its 210,500 kW load.

- Published: 2026-10-26T09:27:56+00:00
- Section: Expansion
- Author: News Desk
- URL: https://newsforagent.com/news/2026-10-26/state-grid-catl-phase-vi-power-line
- Source: [PR Newswire APAC](https://en.prnasia.com/releases/apac/state-grid-changzhou-power-supply-company-helps-accelerate-power-supply-supporting-facilities-for-catl-new-energy-project-again-553209.shtml)

## Key takeaways

- State Grid Changzhou Power Supply Company used drones to send guide ropes across the Nanjing-Hangzhou High-Speed Railway for the 220 kV Ganxi to Shidai Xinke line.
- The N10 to N11 span is 469 meters and crosses a 110 kV line, the Nanxi River, the G25 expressway and the high-speed railway.
- CATL New Energy's Phase VI project has an expected electricity load of approximately 210,500 kW and will receive dual-circuit supply from Ganxi Substation.

State Grid Changzhou Power Supply Company used drones to send guide ropes across the Nanjing-Hangzhou High-Speed Railway twice for the 220 kV line from Ganxi to Shidai Xinke, the company said, preparing for the first ground wire and one phase conductor. The work supports CATL New Energy's Phase VI project, which has an expected electricity load of approximately 210,500 kW.

## Drones Cross the Nanjing-Hangzhou Railway

The N10 to N11 span is 469 meters and crosses, in order, a 110 kV line, the Nanxi River, the G25 Changchun-Shenzhen Expressway and the Nanjing-Hangzhou High-Speed Railway, according to [PR Newswire APAC](https://en.prnasia.com/releases/apac/state-grid-changzhou-power-supply-company-helps-accelerate-power-supply-supporting-facilities-for-catl-new-energy-project-again-553209.shtml). The line runs from Ganxi Substation to the planned Shidai Substation and is erected with double-circuit lines on the same tower.

The railway construction window runs from 0:00 to 4:00 each day, leaving only three hours for the main stringing procedures after blockade, catenary power outage and grounding confirmation, and final inspections. The conductors of the two circuits and the two ground wires are planned to complete crossing deployment over four nights.

Chu Guowei, Director of the Project Management Center of State Grid Changzhou Power Supply Company, said the CATL New Energy Phase VI project plans to build cell production lines as well as module and battery pack assembly lines. "According to the connection plan, when one circuit is withdrawn, the other circuit has the capacity to bear the entire load of the project," Chu said, providing dual-circuit power supply assurance for the project's production.

## Earlier Work by State Grid Changzhou

On October 22, 2026, State Grid Changzhou Power Supply Company provided emergency power assurance to Jiangsu Huapeng Transformer during a planned outage, enabling on-time factory testing and overseas order fulfillment, PR Newswire APAC reported. On October 21, 2026, the company conducted autumn maintenance at Maoshan and Wuyi substations, including transformer capacity expansion and inspections, targeting hidden faults and improving equipment readiness for winter peak demand, according to PR Newswire APAC. On August 27, 2026, the company helped Jiangsu Huapeng Transformer obtain BSI carbon neutral certification for 15 units of 35 kV, 6,000 kVA pad-mounted transformers, the first batch of export-oriented transformers in China to receive it, PR Newswire APAC reported.

## What Comes After the Stringing

After the guide ropes are deployed, tensioning equipment will pull the ropes level by level, completing the deployment and tensioning and attachment of conductors and ground wires in batches, the company said. The two 220 kV circuits will connect Ganxi Substation with the enterprise user substation after the project is completed and commissioned.