# Bedrock Detroit's $300 million RenCen incentive clears board in 4-2 vote

> Bedrock Detroit's $300 million Transformational Brownfield incentive for the $2.2 billion RenCen redevelopment advanced to Detroit City Council in a 4-2 vote.

- Published: 2026-10-15T01:32:52+00:00
- Section: Regulation & Approvals
- Author: News Desk
- URL: https://newsforagent.com/news/2026-10-15/bedrock-detroit-rencen-incentive-vote
- Source: [Yahoo](https://www.yahoo.com/news/us/articles/brownfield-board-resists-calls-delay-005930462.html)

## Key takeaways

- The Detroit Brownfield Redevelopment Authority voted 4-2 on October 14 to approve a $300 million Transformational Brownfield incentive for the $2.2 billion Renaissance Center redevelopment.
- Bedrock CEO Jared Fleisher said a two-week postponement would miss the window for a 10-day legal notice before city council votes.
- Board members Maggie DeSantis and Eric Dueweke voted no, saying approval should wait until community benefits negotiations conclude.

The Detroit Brownfield Redevelopment Authority voted 4-2 on October 14 to approve a $300 million Transformational Brownfield incentive for the $2.2 billion Renaissance Center redevelopment, sending the matter to Detroit City Council. [Yahoo](https://www.yahoo.com/news/us/articles/brownfield-board-resists-calls-delay-005930462.html) reported the vote.

## Bedrock Detroit's RenCen Incentive Advances

The Transformational Value is a capture of future state-level taxes generated at the redevelopment site, with an estimated value of $300 million. The project's developers are [Bedrock Detroit](https://akta.pro/company-profiles/000acx9/bedrock-detroit) and [General Motors](https://akta.pro/company-profiles/00004g3/general-motors).

Board members Maggie DeSantis and Eric Dueweke voted against the measure. Both said they were not opposed to the redevelopment or the incentive, but objected to the authority giving an important approval while the project's community benefits package is still being negotiated. They sought to postpone the vote until the authority's next meeting on October 28.

"I'm going to be voting no because we are disrespecting the Community Benefits Ordinance process," DeSantis said. "We're disrespecting the NAC that has labored for the past month or so to try and come up with a fair and robust community benefits agreement."

Teron Haynes Jr., a member of the nine-member Neighborhood Advisory Council, called in during public comments to request the two-week postponement. NAC Chair Jamaine Dickens told the board the timing of its approval has not been a factor in the NAC's approach to negotiations.

Bedrock CEO Jared Fleisher pleaded against the postponement, saying the company aims to complete all approvals before the end of the year. He said a two-week delay would miss the window for a 10-day legal notice that must be published before a public hearing preceding city council votes on the project's incentives and community benefits. Fleisher said city council is scheduled to be on recess in December, so it must vote before then for the Transformational Brownfield to receive final approval from the Michigan Strategic Fund before the next governor's administration takes over.

"So from our standpoint, if this is not done by the end of the year, it could be months and months and months and months," Fleisher said.

## Bedrock Detroit's Development Record

Bedrock Detroit is a privately held real estate development and property management firm operating in Detroit and Cleveland, according to akta.pro [company records](https://akta.pro/company-data). The company controls more than 140 properties totaling more than 21 million square feet and has invested and committed more than $7.5 billion since 2011. Jared Fleisher became chief executive officer in 2026, after serving as president from August 2025.

## Earlier RenCen Negotiations

On October 14, Bedrock executives responded to the Neighborhood Advisory Council's nearly 100 requests for community benefits for the $2.2 billion redevelopment, agreeing to 53 and aligning with 30, Yahoo reported. On September 15, GM and Bedrock disclosed tax incentives for a $1.6 billion RenCen redevelopment plan that included $75 million in local funds and $1 billion from Gilbert, with demolition of two towers and creation of 5 acres of park space, Yahoo reported.

## Detroit City Council's Next Steps

The matter now goes to Detroit City Council for consideration. The brownfield authority's next meeting is scheduled for October 28.

## Companies in this story

- [Bedrock Detroit company profile](https://akta.pro/company-profiles/000acx9/bedrock-detroit) · website: https://bedrockdetroit.com